5-18    List of Large and Medium-sized Projects Construction and Quota for Innovation and Reformof Capital
(2003 year)
          (10 000yuan)  
  Project         Accumula-tive Investment Actually Made        
Seat of Construction Projects Starting Date Date of   Construction Scale and Newly-Added Production CapaCity
Putting into Operation Total Invest-memt Planned #Investment Made in the Year Accumulative New-added Fixed Assetsform It¨s Start to the Year-end #Newly- Increased Fixed Assets in the Year Name of Production Capal City (or Efficiency) Metering Unit Scale of construction Projects Accumula-tive Newly- Increased Production   
                  CapaCity #In the Present year
Large and Medium Projects in Capital Construction Karamay Oil Refinery, China Petroleum & Natural Gas Ltd.,Co. Karamay City 200302 200311 508259 625585 625585 625585 625585 Natural Crude Oil Prospecting 10 000 tons/year 165.5 165.5 165.5
  Natural Gas Prospecting 100 millionu.m/year 4.45 4.45 4.45
Turpan-Hami Sub-company,China Petroleum & Natural Gas Ltd.,Co. Shanshan County 200102 200312 112661 122435 122435 85178 85178 Natural Crude Oil Prospecting 10 000 tons/year 300 235 37
  Natural Gas Prospecting 100 millioncum/year 15 12.3 2.8
Tarim Oil-field Sub-company, China Petroleum & Natural Gas Ltd.,Co. Korla City 200102 710000 674078 340232 35826 19225 Natural Crude Oil Prospecting 10 000 tons/year 80 80 80
West-East Natural Gas Transmission Construction Headquaters Korla City 200105 345768 273554 177786 273554 95768 Laying Natura-Gas Pipe Kilometer 941 941
Xinjiang Ashele Copper Industrial Ltd.,Co. Habahe County 200204 54800 27689 19914 554 118 Copper Mining 10 000 tons/year 132
  Copper Dressing (1) Crude Ore Processing 10 000 tons/year 132
Shihezi Yinhe Textile Ltd., Co. Shi Hezi City 200108 200302 23386 25380 1583 25380 25380 Cotton Spindle Spindle 50880 50880 50880
Guanghui Industrial Ltd., Co. Urumqi City 200208 68530 53074 44363 48458 42050 Liquefied Natural Gas Standard Cubic Meter/Day 1500000
Xinjiang Tarim Oil Refinery Ltd.,Co. Korla City 199702 334607 340658 2932 7668 Distilling Equipment 10 000 tons/year 250
  Analytical Equipment 10 000 tons/year 80
Xinjang Hong Yanchi No.2 Power Plant Urumqi City 199804 200312 322958 322958 46600 322958 106829 Thermal-Power 10 000 kw/year 80 80 40
Toksun Thermal Power Plant Toksun County 200106 120000 13295 7533 Thermal-Power 10 000 kw/year 50
Haimi Tianguang Power Ltd.,Co. Hami [Kumul] City 200107 97772 80588 15587 57124 56531 Thermal-Power 10 000 kw/year 27 13.5
Xinjiang Jilintai Water Stair Development Ltd.,co. Nilka County 200106 228604 108376 53032 1468 Water-Power 10 000 kw/year 46
Urumqi Natural Gas Engineering Headquaters Urumqi City 200101 55562 49143 18466 Natural Gas Pipe-transmission kilometer 47 47 29
  10 000 cum/year 0.31 0.31 0.19
2nd Stage of Natural Gas Project, Urumqi Gas Corporation Urumqi City 200308 62000 3000 3000 Natural Gas Pipe-transmission kilometer 300 6 6
  10 000 cum/year 10 0.2 0.2
Xinil Reservior Management Office,Xinjiang Bayangol Prefecture Korla City 200003 200310 14690 14690 5653 14690 14690 Reservoir Volume 100 million cu.m 2.2 2.2 2.2
Uruwati Water Diversion Pivotal Works Hotan County 199504 143378 128957 1801 Hydro-power Generation 10 000 kw/year 6 3 3
  Reservoir Volume 100 million cu.m 3.47
  Efficient Irrigating Area 182
Qapuqi Water Diversion Pivotal Works Office Gongliu County 200206 189045 73583 45457 Hydro-power Generation 10 000 kw/year 32
  Reservoir Volume 10 000 cu.m 17.7
  Efficient Irrigating Area 10 000 mu 523.45
Xinjiang Water Conservancy Department,Works of Diverting the water of  the Ertix River to Urumqi Urumqi City 200109 441990 250000 124000 2324 Reservoir Volume 10 000 cu.m 2
Kuytun-sayram Lake Highway Kuytun City 200206 305537 101938 56842 New-built Highway kilometer 303.2
  329 Express Highway kilometer 18
  First class Highway kilometer 229.6
  Second class Highway kilometer 55.6
S306 Bapan Waterwill-Akqi Highway Akqi County 200207 34402 30016 23867 Rebuilt Highway kilometer 259
Xinjiang Korla Airport Reconstruction Works Korla City 200310 44000 3759 3759 Run-way for Civil Aviation Airport Lane 1
  Meter 2800
Renovation and Transformation
Colliery Renovation,Turpan Jinma Ltd.,Co. Toksun County 200206 6000 1142 1142 Crude coal Mining 10 000 tons/year 30
Coal Pit Technical Reform, Hami Coal Industrial Group Changji City 200306 15968 2029 2029 Crude coal Mining 10 000 tons/year 150
2nd and 3rd Projects of Production Line, Maiquer Dairy Products Production Line Changji City 200305 18600 5010 5010 Other Dairy Products ton /year 100000
Xinjiang Changmian Ltd.,Co. Kar-mill yarn Changji City 200204 32939 16747 5649 Cotton Spindle Spindle 50000 10000 10000
Technological Transformation of 36 Introduced open-end Spining Machines,Xinjiang Tianshan Textile Group. Hutubi County 200204 24000 13126 10835 315 315 Jet Weaving Spindle 36
 
100,000 Spindles of Compact Spinning Porject Introduced by Xinjiang Tianshan Cotton Mill Hutubi County 200308 47000 2210 2210 Digital Close-Weaving spindle 100000
70,000 Spindles of Cotton Yarn Extension Project, Xinjiang Cotton, Kashgar Company Kashgar City 200310 25000 12150 12150 Cotton Spindle Spindle 75000
Xinjiang Bosten Lake Reed Industrial (Group) Ltd.,Co. Korla City 200104 200312 25000 25000 8235 25000 8235 Machine-made Pulp 10 000 tons/year 5 5 5
2nd Stage of Extension for Asphelt, Urumqi Tarm Oil Refinery Kuqa County 200308 110000 12000 12000 Oil Refining (Thick Oil) 10 000 tons/year 120
Xinjiang Iron & Steel Corporation,42 holes Coking Oven Works Urumqi City 200211 8000 6080 5930 Coke 10 000 tons/year 26
Iron Plate Works, Xinjiang Steel and Iron Corporation Urumqi City 200308 40000 11000 11000  Cold-Processed Steel Material 75
  Cold-rolled Thin Steel Plate 60
  Galvanized Steel Plate 15
Newly-built 380 Cubic Meters of Furnace, Xinjiang Steel and Iron Corporation Urumqi City 200311 10000 3317 3317 Pig Iron 10 000 tons/year 27
Special Rosin Technical Reform Urumqi City 200301 21280 20508 20508 20508 20508 Caustic Soda tons/year 60000 30000 30000
  Plastic Rosin and Polyaster tons/year 60000 50000 50000
Xinjiang Pharmaceutic Factory Seat-Changjing Transformation Urumqi City 200204 12648 9207 4507 Injection 10 000/year 5000
  Tablets 10 000 tablets/year 150000
  Infusion 10 000 bottles/year 3000
Technology Transformation,Xinjiang Tunhe Building Materials Limited Company Changji City 200204 12000 10854 1510 10854 1510 Plastic Product 10 000 tons/year 40000
Qapqal County Xitianshan Special Cement Industry Qapqal County 200208 200306 3005 3005 5 3005 3005 Cement 100 00 tons /year 11 11 11
Extension on Xinjiang Yelite Group Corporation ans Shi Tuo Luogai Cement Works Yinining City 200304 14000 11250 11250 Cement 100 00 tons /year 30
Glass Products Factory, Urumqi Bobai Industrial Company Urumqi City 200306 14000 251 251 81 81 Beer Bottle tons /year 7000
Composite Material Production Line of Xinjiang Changji Composite Material Corporation Miquan City 200306 15900 1000 1000 520 520 Composite Tube Material 100 00 million/year 100.8
The Second-term Expansion of Electronic Aluminium Foil and Urumqi City 200108 6666 8602 3016 5463 1369 Eltronic Aluminium Foil tons/year 9000
RefinedAluminium,Xinjiang Zhonghe Ltd.,Co. 8331 8331 5162 5162 Aluminium Processing tons /year 949
2nd Stage of Extension for High-Power Electrode Chromium Urumqi City 200302 14000 Aluminium Foil tons/ year 949
Transformation of Large-size Intelligent Transformer,Xinjiang Toban Electric Engineering Changji City 200204 6280 5513 1178 4195 195 Large & Medium Type Transformer 10 000 kev 400 250 8
Thermal Works by ThermoelectriCity Linking Production,Xinjiang Iron & Steel Corporation Urumqi City 200210 30000 22664 21971 Thermal Power Generation 10 000 kw 5
  CapaCity of City Thermal System:Vapor ton/hours 260
  Hot Water megawatt / hour 203
Electrolytic Aluminium & Power Plant,Xinjiang Tianlong Minerals Stock Ltd.,Co. Fukang City 200103 200311 13500 6980 6980 6980 6980 Electrolytic Aluminium tons /year 2 2 2
  Thermal Power Generation 10 000 kw 2.5 2.5 2.5
Fukang City Power Plant 105kw Generation Unit Fukang City 199804 200310 40707 33510 1500 33510 1500 Thermal Power Generation 10 000 kw 10 10 10
Da Bancheng No.1 Wind power Plant Expansion Works Da Bancheng District 200206 16311 7395 5459 5426 5416 Others Generation 10 000 kw 2.28
The Fifth-term CapaCity Expansion Works for Gsm,XinjiangMobile Telecommunications Urumqi City 200110 200310 161000 161000 46000 161000 161000 Mobil Communicating unit/year 528 528 528
                  Base Station